City centre hotel, London
A flagship 412-key hotel in central London delivered through a steel framed pod programme, reducing site trades and accelerating the fit-out programme.

Location
London, UK
Client
Tier-1 main contractor
System
Steel framed
Duration
18 months
Project outcomes
412
Pods delivered
14
Weeks saved
0
Re-worked bathrooms
The hotel brief called for a high-end tiled bathroom with varied layouts across standard, accessible and suite rooms. Each pod was engineered on a heavy-gauge steel frame, with walls finished to the architect's exact specification in the factory.
By moving the majority of bathroom trades off site, the programme avoided the congestion and sequencing conflicts that typically slow hotel fit-outs. Pods arrived fully tested, with MEP connections prepared for rapid hook-up.
Challenges
What the project needed to solve.
- 01
Restricted city centre site with limited crane windows and storage.
- 02
Architect-specified tiled finishes requiring consistent grout lines and layout.
- 03
Tight programme tied to hotel opening date.