Steel lead time

Order to site in
twenty-eight weeks.

The complete programme for a premium steel framed, fully tiled bathroom pod — from contract award through to just-in-time delivery to your crane.

20+ years manufacturing200,000+ pods delivered
Walker Modular steel framed bathroom pod

Steel pod programme

Order to site — 28 weeks

Week 0 → Week 28

4 weeks

Design

5 weeks

Procurement

3 weeks

Prototype

4 weeks

Frame

8 weeks

Fit-out

2 weeks

QA

2 weeks

Dispatch & delivery

Stage by stage

Nine stages.
Twenty-eight weeks. One standard.

Every steel framed pod follows the same rigorous, repeatable path — because a predictable process is what makes a predictable programme.

  1. 01 · Week 0

    Duration: 1 week

    Order & project kick-off

    Contract award, project team introduced, programme aligned to your construction sequence and floor-by-floor delivery plan.

  2. 02 · Weeks 1–3

    Duration: 3 weeks

    Specification & design freeze

    Tile selection, sanitaryware, brassware, IPS panels and M&E all locked. Full CAD technical drawings issued and formally signed off.

  3. 03 · Weeks 4–8

    Duration: 5 weeks

    Procurement

    Long-lead items released first — specified tiles, brassware, doors and steel sections. All schedules approved against the frozen design.

  4. 04 · Weeks 9–11

    Duration: 3 weeks

    Prototype pod & sign-off

    A fully tiled, fully finished sample pod built, inspected and formally signed off by client, architect and M&E consultant.

  5. 05 · Weeks 12–15

    Duration: 4 weeks

    Steel frame fabrication

    Heavy-gauge C-section subframes cut, welded and finished in-house to millimetre tolerance. Every frame checked before fit-out release.

  6. 06 · Weeks 16–23

    Duration: 8 weeks

    Manufacture & fit-out

    M&E first fix, wall build-up, full tiling, sanitaryware, brassware, doors, mirrors, joinery and ironmongery — all installed in the factory.

  7. 07 · Weeks 24–25

    Duration: 2 weeks

    Quality assurance

    Every pod water-tested, electrically tested and photographed against a documented digital QA checklist. Traceable, pod-by-pod.

  8. 08 · Week 26

    Duration: 1 week

    Dispatch

    Pods wrapped, protected and loaded onto our own fleet. Delivery scheduled to your crane availability, not the other way round.

  9. 09 · Weeks 27–28

    Duration: 1–2 weeks

    Delivery to site

    Our trained drivers deliver just-in-time to the tower. Craned into position ready for follow-on trades — on time, in full, every time.

Why 28 weeks

A tiled bathroom,
built like an aircraft.

A specified steel framed pod carries the same wet-trade sequence as a site-built bathroom — steel frame, wall build-up, tiling, grouting, sanitaryware and joinery — but delivered under factory conditions with photographic QA against every pod.

The additional weeks are spent on procurement of long-lead specified finishes and on the tiling and fit-out programme that determines the architectural quality of the finished bathroom.

Walker Modular factory floor

Compare systems

GRP pod?
20-week programme.

One-piece moulded GRP pods compress the programme by eliminating the wet-trade fit-out sequence — see the full 20-week timeline.